Uisce Éireann, is progressing with works to upgrade the Sewerage Scheme Network in Buncrana & Ballybofey - Stranorlar, Co. Donegal.

Uisce Éireann, working in partnership with Donegal County Council, is progressing with works to upgrade the Buncrana and Ballybofey-Stranorlar Sewerage Schemes.

The €31 million investment involves an upgrade to the wastewater network infrastructure in Buncrana and Ballybofey-Stranorlar, reducing the risk of sewer flooding and addressing non-compliant sewer overflows into Lough Swilly and the River Finn. It will also improve the capacity of the sewer network allowing for current and future population growth, and supporting the social and economic development of Buncrana, Ballybofey-Stranorlar and the surrounding area. Stormwater storage will be provided in Buncrana to reduce the risk of overflows during storms.

Both schemes are part of the Donegal Towns & Villages Sewerage Schemes. 

These works will ensure compliance with EU Urban Wastewater Treatment Directive and the EPA Wastewater Discharge License Emission Limit Values, and will eliminate non-compliant combined sewer overflows within the area. Ward & Burke Water Limited will carry out the works on behalf of Uisce Éireann. Works are due for completion by the end of 2024.

Location
Donegal
Status
In progress
Type
Wastewater

What are the benefits of this project?

The upgrade works carried out as part of this project will:

  • Reduce the risk of overflows and flooding during heavy rain events through provision of stormwater storage.
  • Improve water quality in the receiving waters.
  • Ensure compliance with Urban Wastewater Treatment Regulations 2001 and the EPA Wastewater Discharge Licencing.
  • Ensure any discharge to Lough Swilly and the River Finn meets all appropriate discharge standards.
  • Provide for growth and development in Buncrana, Ballybofey, Stranorlar and the surrounding areas.

What is involved as part of this project?

The proposed schemes will include the following:

Buncrana Sewerage Scheme:

  • Provision of stormwater storage at the Buncrana Wastewater Treatment Plant and at the Westbrook Pumping Station.
  • Upgrade of the sewer network (c.3km) to increase its capacity.
  • Upgrades to the existing pumping stations at Westbrook, Derry Rd, Ludden, Earlsfort and The Pier.
  • Decommission 2 existing storm overflows.
  • As part of this project, it is planned that works will take place in the following locations including: Marian Park, Cahir O 'Doherty Avenue, Aileach Road, Railway Road, Cockhill Road and Castle Avenue.

Ballybofey-Stranorlar Sewerage Scheme:

  • Replace the existing pumping station at Navenny.
  • Upgrades to the existing St Joseph's Pumping Station and Glenfinn Rd Pumping Station.
  • Upgrade of the sewer network (c.2km) to increase its capacity.
  • Decommission 2 existing storm overflows.
  • As part of this project it is planned that works will take place in the following locations including: Chapel Lane, Stranorlar Main Street, Navenny Road, Chestnut Road, St Joseph's Pumping Station.

Works in Ballybofey - Stranorlar

Commencement DatePlanned 
Completion Date
Planned WorksTraffic Management 
5th March 2023February 2025Site Offices & CompoundNo Traffic Management
Location: Navenny, Ballybofey
20th March 2023 January 2025Upgrade of St Joseph's PSNo Traffic Management
Location: Millbrae Road, Ballybofey
20th March 2023February 2025Upgrade of Navenny PSFootpath Closure Intermittently to Facilitate Works 
Location: Navenny, Ballybofey
22nd August 2024January 2025Upgrade of Glenfin PSSingle Lane Closure to Facilitate ESB Works 
- Date TBC

Works in Buncrana

Commencement DatePlanned Completion DatePlanned WorksTraffic Management 
27th March 2023February 2024 (provisional)Mobilisation of Site Offices 
& Compound
No Traffic Management 
Location: Ferris Lane, Buncrana
3rd April 2023December 2024Westbrook Pumping Station 
– Upgrade of Station Works
Footpath Closure Intermittently to Facilitate Works
Location: Westbrook PS – 
Entrance of Westbrook Road 
31st October 2023March 2025Construction of New 
Storm Water Holding Tanks 
No Traffic Management, 
Works Taking Place in WWTP. 
29th October 2024November 2024Minor Upgrades to The Pier PSNo Traffic Management